SLRI Machine Status Accelerator Operation Cryogenics
  Operation E-Logbook, Page 430 of 430  Not logged in Accelerator E-Logbook
ID Date Author Event Time Typeup Section Icon Subject Status RTime (min)
  12868   Mon 30 May 2016 08:50:31 Somkiat Wisaiphion Mon 30 May 2016 08:38:19 RoutineOperation Note Stop Injection @ 153.2 mA  
  12869   Mon 30 May 2016 08:50:48 Somkiat Wisaiphion Mon 30 May 2016 08:46:37 RoutineOperation Note Ramp up energy and close MPW gap complete @ 151 mA  
  12870   Mon 30 May 2016 08:51:07 Somkiat Wisaiphion Mon 30 May 2016 08:48:53 RoutineBeam Dynamics Note SPS Orbit Control System Complete@ 150.1 mA  
  12871   Mon 30 May 2016 20:48:16 Sarawut Chitthaisong Mon 30 May 2016 20:02:05 RoutineOperation Note Test injection SYN >>> OK. (Isyn = 26 mA)  
  12872   Mon 30 May 2016 20:48:35 Sarawut Chitthaisong Mon 30 May 2016 20:30:21 RoutineOperation Note Dump Beam @ 67.9 mA  
  12873   Mon 30 May 2016 20:49:02 Sarawut Chitthaisong Mon 30 May 2016 20:31:40 RoutineOperation Note Warm up HBT,STR,MPW,SWLS Magnets  

Flush TPG 1 cycle

  12874   Mon 30 May 2016 20:49:30 Sarawut Chitthaisong Mon 30 May 2016 20:38:07 RoutineOperation Note Start Injection  

Max rate = 125.2 mA/min

  12875   Mon 30 May 2016 20:49:53 Sarawut Chitthaisong Mon 30 May 2016 20:40:36 RoutineOperation Note Stop Injection @ 153.2 mA  
  12876   Mon 30 May 2016 20:50:11 Sarawut Chitthaisong Mon 30 May 2016 20:47:58 RoutineOperation Note Ramp up energy and close MPW gap complete @ 150.1 mA  
  12877   Mon 30 May 2016 20:50:33 Sarawut Chitthaisong Mon 30 May 2016 20:50:16 RoutineBeam Dynamics Note SPS Orbit Control System Complete@ 149.5 mA  
  12878   Tue 31 May 2016 08:40:13 Somkiat Wisaiphion Tue 31 May 2016 08:30:02 RoutineOperation Note Dump Beam @ 68.4 mA  
  12879   Tue 31 May 2016 08:40:32 Somkiat Wisaiphion Tue 31 May 2016 08:32:18 RoutineOperation Note Warm up HBT,STR,MPW,SWLS Magnets  

Flush TGP 1 cycle

  12880   Tue 31 May 2016 08:41:51 Somkiat Wisaiphion Tue 31 May 2016 08:37:03 RoutineOperation Note Start Injection  

Max rate 116 mA/Min.

  12881   Tue 31 May 2016 08:42:05 Somkiat Wisaiphion Tue 31 May 2016 08:39:56 RoutineOperation Note Stop Injection @ 152.5 mA  
  12882   Tue 31 May 2016 08:47:56 Somkiat Wisaiphion Tue 31 May 2016 08:47:45 RoutineOperation Note Ramp up energy and close MPW gap complete @ 149.9 mA  
  12883   Tue 31 May 2016 08:50:32 Somkiat Wisaiphion Tue 31 May 2016 08:49:21 RoutineBeam Dynamics Note SPS Orbit Control System Complete@ 149.3 mA  
  12884   Tue 31 May 2016 20:56:13 Apiwat Pinyoyang Tue 31 May 2016 20:12:45 RoutineOperation Note Test injection SYN >>> OK. (Isyn = 28 mA)  
  12885   Tue 31 May 2016 20:57:26 Apiwat Pinyoyang Tue 31 May 2016 20:33:28 RoutineOperation Note Dump Beam @ 70.2 mA  
  12886   Tue 31 May 2016 20:58:18 Apiwat Pinyoyang Tue 31 May 2016 20:34:34 RoutineOperation Note Warm up HBT,STR,MPW,SWLS Magnets  

Flush TGP 1 cycle

  12887   Tue 31 May 2016 20:59:07 Apiwat Pinyoyang Tue 31 May 2016 20:41:27 RoutineOperation Note Start Injection  

Max rate = 125 mA/min

  12888   Tue 31 May 2016 20:59:39 Apiwat Pinyoyang Tue 31 May 2016 20:43:13 RoutineOperation Note Stop Injection @ 151.3 mA  
  12889   Tue 31 May 2016 21:00:19 Apiwat Pinyoyang Tue 31 May 2016 20:51:56 RoutineOperation Note Ramp up energy and close MPW gap complete @ 148.7 mA  
  12890   Tue 31 May 2016 21:01:02 Apiwat Pinyoyang Tue 31 May 2016 20:53:39 RoutineOperation Note SPS Orbit Control System Complete@ 148.1 mA  
Accelerator Technology Division | Synchrotron Light Research Institute (Public Organization) | Powered by ELOG V3.1.1