  Operation E-Logbook, Page 430 of 430  Not logged in Accelerator E-Logbook
ID Date Author Event Time Type Section Icon Subject Statusup RTime (min)
  628   Wed 18 Apr 2012 13:30:50 Natthawut Suradet Mon 16 Apr 2012 06:27:55 ProblemControl Reply Re: CNT-SRV crash every few daysUnder Process 

Scan and remove KIDO worm from control room computers.

There are 2 computers infects.

- STR RF Remote control @ control room 2

- OPC-SRV @ control room 2

Under progress for observe more problem.

  775   Thu 26 Apr 2012 23:35:12 Natthawut Suradet Thu 26 Apr 2012 23:31:33 ProblemControl Warning Swap IP of CNT-SRV to DLG-SRV2Under Process 

 ทดลองปิดระบบเครือข่ายเครื่อง CNT-SRV

และ Set IP เครื่อง DLG-SRV2 เป็น 192.168.100.11 (เดิม 192.168.100.16)

เพื่อทดสอบปัญหาเครื่อง CNT-SRV restart เอง

****อยู่ในระหว่างทดสอบ****

  776   Fri 27 Apr 2012 08:17:40 Natthawut Suradet Fri 27 Apr 2012 08:15:57 ProblemControl Reply Re: Swap IP of CNT-SRV to DLG-SRV2Under Process 

Natthawut Suradet wrote:

 ทดลองปิดระบบเครือข่ายเครื่อง CNT-SRV

และ Set IP เครื่อง DLG-SRV2 เป็น 192.168.100.11 (เดิม 192.168.100.16)

เพื่อทดสอบปัญหาเครื่อง CNT-SRV restart เอง

****อยู่ในระหว่างทดสอบ****

 @27/04/2012 8.05 ระบบใหม่ สถานะไม่สามารถทำงานได้

ย้ายระบบกลับเป็นระบบเดิม

  790   Sat 28 Apr 2012 08:14:14 Natthawut Suradet Sat 28 Apr 2012 08:14:13 ProblemControl Reply Re: Swap IP of CNT-SRV to DLG-SRV2Under Process 

Natthawut Suradet wrote:

Natthawut Suradet wrote:

 ทดลองปิดระบบเครือข่ายเครื่อง CNT-SRV

และ Set IP เครื่อง DLG-SRV2 เป็น 192.168.100.11 (เดิม 192.168.100.16)

เพื่อทดสอบปัญหาเครื่อง CNT-SRV restart เอง

****อยู่ในระหว่างทดสอบ****

 @27/04/2012 8.05 ระบบใหม่ สถานะไม่สามารถทำงานได้

ย้ายระบบกลับเป็นระบบเดิม

 @28/04/2012 8.10 ย้ายระบบสมบูรณ์

นำไฟล์ของเครื่อง CNT-SRV ไป Share ไว้ที่เครื่อง OPR-PC1 (D:\CNT-SRV)

map network drive "I" ที่เครื่อง OPR-PC2, OPR-PC3 มายัง OPR-PC1

 

 

ทดสอบ Warm up magnet ได้ไม่มีปัญหา

--------------------------

 

  791   Sat 28 Apr 2012 08:15:58 Natthawut Suradet Sat 28 Apr 2012 08:14:43 ProblemControl Warning Disconnect CNT-SRV local area networkUnder Process 

  ถอดสาย lan เครื่อง CNT-SRV ออก เพื่อทดสอบปัญหาเครื่อง restart เอง

  945   Mon 07 May 2012 21:19:29 Somkiat Wisaiphion Mon 07 May 2012 09:00:00 InstallationRF Note Install X-RAY measurement by Dr.NawinUnder Process 
  1106   Sat 12 May 2012 17:49:04 Somkiat Wisaiphion Sat 12 May 2012 17:32:00 Measured ParameterBeam Dynamics Note Record/ parameters (Porntip)Under Process 
  1538   Wed 08 Aug 2012 01:18:34 Somkiat Wisaiphion Wed 06 Jun 2012 13:30:00 ConfigurationLINAC Note Change electron gun of LinacUnder Process 
  1564   Thu 09 Aug 2012 02:16:34 Somkiat Wisaiphion Wed 04 Jul 2012 02:15:34 ProblemOperation Note SYN-OF fet fuse broken (fet #4)Under Process 
  2096   Mon 27 Aug 2012 22:48:07 Somkiat Wisaiphion Mon 27 Aug 2012 16:50:00 ProblemMagnet Note No beam at SYN (Booter)Under Process 

 Check SYN-BM-PS (Output wave form is different from before, normally 10 V but now 8 V )

  2208   Tue 11 Sep 2012 08:55:32 Somkiat Wisaiphion Mon 03 Sep 2012 15:45:00 ProblemMagnet Note SYN-BM not workingUnder Process 

 Check BM-PS at ESS room

Found that SYN-BM, QM pattern are not loaded

  2305   Fri 14 Sep 2012 09:03:58 Somkiat Wisaiphion Thu 13 Sep 2012 08:45:00 Measured ParameterOther Note Dr.Nawin do experiment with booster SYNUnder Process 

 Change pattern to 1.2 ms and 4 sec cycle

Measure before tune of SYN 

  2403   Wed 19 Sep 2012 21:21:06 Somkiat Wisaiphion Tue 18 Sep 2012 21:06:00 RoutineOperation Note Ramping Energy up 1.2 GeVUnder Process 
  2410   Wed 19 Sep 2012 21:24:06 Somkiat Wisaiphion Wed 19 Sep 2012 08:51:00 RoutineOperation Note Ramping Energy up 1.2 GeVUnder Process 
  2419   Wed 19 Sep 2012 21:27:44 Somkiat Wisaiphion Wed 19 Sep 2012 20:28:00 RoutineOperation Note Ramping Energy up 1.2 GeVUnder Process 
  2426   Thu 20 Sep 2012 20:26:36 Somkiat Wisaiphion Thu 20 Sep 2012 09:22:00 RoutineOperation Note Ramping Energy up 1.2 GeVUnder Process 
  2429   Thu 20 Sep 2012 20:29:24 Somkiat Wisaiphion Thu 20 Sep 2012 16:52:00 OtherRF Note Test Y-RF by Dr.RoengrutUnder Process 
  2435   Thu 20 Sep 2012 20:30:47 Somkiat Wisaiphion Thu 20 Sep 2012 20:17:00 RoutineOperation Note Ramping Energy up 1.2 GeVUnder Process 
  2458   Fri 21 Sep 2012 21:05:45 Somkiat Wisaiphion Fri 21 Sep 2012 20:50:00 RoutineOperation Note Ramping Energy up 1.2 GeVUnder Process 
  2475   Sat 22 Sep 2012 20:26:08 Somkiat Wisaiphion Sat 22 Sep 2012 20:16:00 RoutineOperation Note Ramping Energy up 1.2 GeVUnder Process 
  3631   Thu 13 Dec 2012 14:57:47 Natthawut Suradet Thu 13 Dec 2012 14:35:49 ConfigurationControl Warning Stop STR DCCT interface programUnder Process 

Stop STR DCCT interface program

for upgrade new version...

 

Pop

  4198   Tue 12 Mar 2013 15:36:14 Natthawut Suradet Tue 12 Mar 2013 15:17:04 DevelopmentControl Note Stop Data Logger Program @DLG-SRV1Under Process 

Stop data logger for replace a new version.

 

  4377   Wed 20 Mar 2013 09:27:56 Natthawut Suradet Thu 14 Mar 2013 15:45:17 DevelopmentBeam Diagnostics Note Force error calculation data on Beam Profile MonitorUnder Process 

ปรับปรุงระบบ โดยการเพิ่มการตรวจสอบ ค่า Sigma X,Y และ Coordinate X,Y

ถ้าค่าที่คำนวณได้ไม่อยู่ใน range ที่กำหนด ให้เอาค่าที่คำนวณได้ที่ถูกต้องก่อนหน้านี้มาแสดงและ log ข้อมูลที่ถูกต้อง

 

 

อยู่ระหว่างการติดตามผล

Attachment 1: 20130320-beam_profile_monitor.png
20130320-beam_profile_monitor.png
Accelerator Technology Division | Synchrotron Light Research Institute (Public Organization) | Powered by ELOG V3.1.1