Message ID: 6281     Entry time: Thu 14 Feb 2019 22:31:51
Author: Chanwawit Somprasong 
Event Time:Thu 14 Feb 2019 22:10:08 
Type: Beam Operation 
Section: Machine Operation 
Icon: Note 
Subject: Beam Injection  
Status: Completed 
RTime (min):  

 

 

 

 

 

18:19 BL-8 request time 10 min

19:30 Water cooling linac have problem

21:58Test run SYN >>OK (Isyn = 10 mA)

22:10 Stop SOFB @ 77.7 mA.

22:11 Warm up HBT magnet, Set parameter for injection, Open MPW gap

22:13 Start injection (Max rate = 13 mA/min) 

22:22 Stop injection @ 150 mA

22:26 Set parameter for store and close MPW gap completed.

22:28 SOFB completed