  Accelerator E-Logbook, Page 1 of 86  Not logged in Accelerator E-Logbook
ID Date Author Event Time Type Section Icon Subject Status RTime (min) Text Attachments
  6652   Wed 13 Nov 2019 08:11:17 Somkiat Wisaiphion Wed 13 Nov 2019 08:00:03 Beam OperationMachine Operation Note Beam Injection  08:00 Stop SOFB @ 81 mA

08:01 Set parameter for injection,
Open MPW gap . OFF RAMP STR-RF.
  
  6651   Tue 12 Nov 2019 20:16:45 Apiwat Pinyoyang Tue 12 Nov 2019 20:10:54 Beam OperationMachine Operation Note Beam injectionCompleted 19:45 Test run SYN >>> OK (Isyn
= 32 mA). 

19:50 BL-5 request time 10 min.
  
  6650   Tue 12 Nov 2019 08:31:31 Apiwat Pinyoyang Tue 12 Nov 2019 08:10:21 Beam OperationMachine Operation Idea Beam injectionCompleted 07:45 BL-1.1 request time 10 min.

         
Test run SYN => OK (Isyn = 34 mA)
  
  6649   Mon 11 Nov 2019 20:25:15 Apiwat Pinyoyang Mon 11 Nov 2019 20:00:05 Beam OperationLINAC Idea Beam injectionCompleted 19:50 Test run SYN >>> OK (Isyn
= 36 mA). 

20:00
  
  6648   Mon 11 Nov 2019 08:24:27 Apiwat Pinyoyang Mon 11 Nov 2019 08:10:06 Beam OperationMachine Operation Note Beam injectionCompleted 04:00 BL-1.1 request time 10 min.

07:40 Test run SYN => OK (Isyn
= 34 mA)
  
  6647   Sun 10 Nov 2019 20:06:11 Nitisart Kumdee Sun 10 Nov 2019 20:00:12 Beam OperationMachine Operation Note Beam InjectionCompleted 19:33 Test run SYN >>> OK (Isyn
= 34 mA). 

20:00 Stop SOFB @ 80.02 mA.
  
  6646   Sun 10 Nov 2019 08:11:53 Nitisart Kumdee Sun 10 Nov 2019 08:00:57 Beam OperationMachine Operation Note Beam InjectionCompleted  

07:30 Test run SYN => OK (Isyn
= 30 mA)
  
  6645   Sat 09 Nov 2019 20:30:54 Nitisart Kumdee Sat 09 Nov 2019 20:10:46 Beam OperationMachine Operation Note Beam InjectionCompleted 19:30 Test run SYN >>> OK (Isyn
= 20 mA). 

19:57 BL1.1 request time 10 min.
  
  6644   Sat 09 Nov 2019 08:25:07 Somkiat Wisaiphion Sat 09 Nov 2019 08:01:53 Beam OperationMachine Operation Note Beam Injection  08:00 Dump beam @ 80 mA

*** Reset LLRF-HPGA hight rf refect 

08:18 Start injection (Max
  
  6643   Fri 08 Nov 2019 20:10:24 Somkiat Wisaiphion Fri 08 Nov 2019 20:00:10 Beam OperationMachine Operation Note Beam Injection  08:00 Stop SOFB @ 82 mA.   

08:01 Set parameter for injection,
Open MPW gap 
  
  6642   Fri 08 Nov 2019 08:40:42 Somkiat Wisaiphion Fri 08 Nov 2019 08:00:26 Beam OperationMachine Operation Note Beam Injection  08:00 Stop SOFB @ 69 mA.   

08:05 Warm up HBT magnet,
Set parameter for injection, Open MPW gap 
  
  6641   Thu 07 Nov 2019 16:55:52 Nitisart Kumdee Thu 07 Nov 2019 16:52:34 ProblemRF Warning Beam dump @91.63 mA / STR-RF faultFixed4416:52 Beam
dump @91.62 mA / STR-RF and H-BH-M1 fault
/ Reset OK.
  
  6640   Thu 07 Nov 2019 08:14:15 Somkiat Wisaiphion Thu 07 Nov 2019 08:00:03 Beam OperationMachine Operation Note Beam Injection  08:00 Stop SOFB @ 80 mA.   

08:01 Warm up HBT magnet,
Set parameter for injection, Open MPW gap 
  
  6639   Wed 06 Nov 2019 09:08:58 Apiwat Pinyoyang Wed 06 Nov 2019 06:48:04 ProblemMagnet Warning Beam InjectionCompleted2106:48 Test run syn >>> OK (Isyn
= 25 mA).

07:50 H-BH-M1 fault  / Reset
  
  6638   Mon 04 Nov 2019 12:06:24 Apiwat Pinyoyang Mon 04 Nov 2019 11:21:51 ProblemMagnet Warning H-BH-M1 faultCompleted 11:21 H-BH-M1 fault (Main error) / Reset
>>> OK.
  
  6637   Mon 04 Nov 2019 08:34:08 Apiwat Pinyoyang Mon 04 Nov 2019 08:14:50 ProblemMagnet Warning H-BV-M2 faultCompleted 08:14 H-BV-M2 fault (water flow) / Reset
>>> OK.

         
  
  6636   Thu 31 Oct 2019 20:14:57 Apiwat Pinyoyang Thu 31 Oct 2019 20:00:47 Beam OperationMachine Operation Note Beam injectionCompleted 19:40 Test run SYN >>> OK (Isyn
= 20 mA). 

20:00 Stop SOFB @ 81 mA.
  
  6635   Thu 31 Oct 2019 08:11:52 Chanwawit Somprasong Thu 31 Oct 2019 07:44:32 Beam OperationMachine Operation Warning Beam dump Completed1607:14 Test run SYN >>> OK (Isyn
= 34 mA). 

07:44 Beam drump @ 82.55 mA : STR-RF
  
  6634   Wed 30 Oct 2019 20:37:44 Apiwat Pinyoyang Wed 30 Oct 2019 20:00:37 Beam OperationMachine Operation Note Beam injectionCompleted 19:40 Test run SYN >>> OK (Isyn
= 36 mA). 

19:50 BL-8 request time 10 min.
  
  6633   Wed 30 Oct 2019 08:22:07 Chanwawit Somprasong Wed 30 Oct 2019 08:05:45 Beam OperationMachine Operation Note Beam InjectionCompleted 06:35  BL-2.2 request time 5 min

07:23  BL-8 request time 10
min
  
  6632   Tue 29 Oct 2019 20:13:59 Chanwawit Somprasong Tue 29 Oct 2019 20:00:13 Beam OperationMachine Operation Note Beam InjectionCompleted 19:08 Test run SYN  = 30 mA 

20:00 Stop SOFB @ 107.7 mA , set
parameter , warm up HBT . 
  
  6631   Tue 29 Oct 2019 15:00:27 Somkiat Wisaiphion Tue 29 Oct 2019 14:42:09 Beam OperationMachine Operation Warning Beam dump Completed1814:42 Beam dump @ 102 mA

14:45 Warm up HBT magnet, Set parameter
for injection, Open MPW gap 
  
  6630   Tue 29 Oct 2019 08:41:37 Apiwat Pinyoyang Tue 29 Oct 2019 08:00:23 Beam OperationMachine Operation Idea Beam injectionCompleted 07:40 Test run SYN >>> OK (Isyn
= 34 mA). 

08:00 Stop SOFB @ 80 mA. 
  
  6629   Mon 28 Oct 2019 20:23:04 Apiwat Pinyoyang Mon 28 Oct 2019 20:10:38 Beam OperationMachine Operation Note Beam injectionCompleted 19:40 Test run SYN >>> OK (Isyn 
= 36 mA ).

19:48  BL-2 request time 10
  
  6628   Mon 28 Oct 2019 08:59:54 Chanwawit Somprasong Mon 28 Oct 2019 08:00:21 Beam OperationMachine Operation Warning Dump beam Completed1307:30 Test run SYN >>> OK (Isyn
= 34 mA). 

 
  
  6627   Sun 27 Oct 2019 20:26:26 Somkiat Wisaiphion Sun 27 Oct 2019 20:13:10 Beam OperationMachine Operation Note Beam Injection  19:18  BL-1.1 request time 10min.

20:13 Stop SOFB @ 70.21 mA
, set parameter , warm up HBT . 
  
  6626   Sun 27 Oct 2019 08:16:28 Apiwat Pinyoyang Sun 27 Oct 2019 08:00:15 Beam OperationMachine Operation Note Beam injectionCompleted 07:40 Test run SYN >>> OK (Isyn
= 38 mA).

08:00 Stop SOFB @ 103 mA.
  
  6625   Sun 27 Oct 2019 02:55:52 Apiwat Pinyoyang Sun 27 Oct 2019 02:36:35 ProblemRF Warning Beam dumpCompleted2602:36 Beam dump @ 95 mA / STR-RF fault
/ Reset >>> OK.

02:45 Warm up HBT, Set parameter,
  
  6624   Sat 26 Oct 2019 20:24:29 Chanwawit Somprasong Sat 26 Oct 2019 20:10:23 Beam OperationMachine Operation Note Beam InjectionCompleted 19:20 Test run SYN  = 34 mA 

19:23  BL-1.2 request time
10min.
  
  6623   Sat 26 Oct 2019 08:17:16 Nitisart Kumdee Sat 26 Oct 2019 08:00:02 Beam OperationMachine Operation Note Beam injectionCompleted 07:43 Test run SYN >>> OK (Isyn
= 34 mA).

08:00 Stop SOFB @ 65.96 mA.
  