  Accelerator E-Logbook, Page 1 of 57  Not logged in Accelerator E-Logbook
ID Date Author Event Time Type Section Icon Subject Status RTime (min) Text Attachments
  5791   Thu 18 Jan 2018 08:37:01 Tewarit Praneetponkrung Thu 18 Jan 2018 08:00:44 Beam OperationMachine Operation Note Beam Injection   08:00 Dump beam @ 63.9 mA.

08:00 Warm up HBT, STR, MPW and
SWLS magnets.
 2018-01-18-0848.PNG 
  5790   Tue 16 Jan 2018 07:51:32 Nitisart Kumdee Tue 16 Jan 2018 06:45:00 Beam OperationMachine Operation Note Beam Injection Completed5306:45 Dump beam @ 10 m.A.

06:47 Warm up HBT, STR, MPW
and SWLS magnets.
 2018-01-16-0744.PNG 
  5789   Tue 16 Jan 2018 07:49:36 Nitisart Kumdee Tue 16 Jan 2018 06:35:00 Beam OperationMachine Operation Warning Beam drop from 64.9 mA to 10 mACompleted 06:35 Beam drop from 64.9 mA to 10
mA / Unknown
  
  5788   Tue 16 Jan 2018 07:41:49 Nitisart Kumdee Tue 16 Jan 2018 02:08:00 Beam OperationMachine Operation Warning Beam drop from 82.50 to 78.62 mACompleted 02:08 Beam drop from 82.50 mA to 78.92
mA / Unknown
  
  5787   Mon 15 Jan 2018 08:52:16 Nitisart Kumdee Mon 15 Jan 2018 08:00:43 Beam OperationMachine Operation Note Beam Injection Completed 07:30 Test run SYN only (Isyn =  10
mA)

08:00 Dump beam @ 77.39 m.A.
 2018-01-15-0858.PNG 
  5786   Sun 14 Jan 2018 20:32:42 Nitisart Kumdee Sun 14 Jan 2018 20:00:00 Beam OperationMachine Operation Note Beam InjectionCompleted 19.13 Test run SYN (Isyn 12 mA)

20.00 Dump beam @ 77.14 mA

20.02 Warm up HBT, STR, MPW
 2018-01-14-2046.PNG 
  5785   Sun 14 Jan 2018 08:33:42 Apiwat Pinyoyang Sun 14 Jan 2018 08:00:39 Beam OperationMachine Operation Note Beam Injection Completed 07:30 Test run SYN only (Isyn =  20
mA)

08:00 Dump beam @ 77 m.A.
 2018-01-14-0841.PNG 
  5784   Sat 13 Jan 2018 20:19:30 Somkiat Wisaiphion Sat 13 Jan 2018 20:00:17 Beam OperationMachine Operation Note Beam Injection   19.13 Test run SYN (Isyn 12 mA)

20.00 Dump beam @ 77.3 mA

20.02 Warm up HBT, STR, MPW
 2018-01-13-2039.PNG 
  5783   Sat 13 Jan 2018 08:35:01 Tewarit Praneetponkrung Sat 13 Jan 2018 08:00:46 Beam OperationMachine Operation Note Beam Injection   07.30 Test run SYN only >>> OK

08:02 Dump beam @ 76.5 m.A.

08:03 Warm up HBT, STR, MPW and
 2018-01-13-0845.PNG 
  5782   Fri 12 Jan 2018 20:09:54 Tewarit Praneetponkrung Fri 12 Jan 2018 20:00:39 Beam OperationMachine Operation Note Beam Injection   19.30 Test run SYN (Isyn 10 mA)

20.01 Dump beam @ 73.9 mA

20.03 Warm up HBT, STR, MPW
 2018-01-12-2043.PNG 
  5781   Fri 12 Jan 2018 08:33:12 Tewarit Praneetponkrung Fri 12 Jan 2018 08:00:46 Beam OperationMachine Operation Note Beam Injection    

08:01 Dump beam @ 66.0 m.A.

08:03 Warm up HBT, STR, MPW
 2018-01-12-0842.PNG 
  5780   Fri 12 Jan 2018 07:54:25 Tewarit Praneetponkrung Fri 12 Jan 2018 17:55:56 ProblemElectrical Note Beam dump @ 83.3 mAFixed - Electricity Unstable

- H-BH1,2 Fault

- Y-QF, Y-QD Fault
  
  5779   Thu 11 Jan 2018 09:08:41 Somkiat Wisaiphion Thu 11 Jan 2018 08:00:25 Beam OperationMachine Operation Note Beam Injection   07:26 Test run SYN only (Isyn = 
20 mA)

08:01 Dump beam @ 64 m.A.
 2018-01-11-0900.PNG 
  5778   Wed 10 Jan 2018 20:54:16 Somkiat Wisaiphion Wed 10 Jan 2018 20:00:20 Beam OperationMachine Operation Note Beam Injection   19.20 Test run SYN (Isyn 15 mA)

20.02 Dump beam @ 61.2 mA

20.04 Warm up HBT, STR, MPW
 2018-01-10-2052.PNG 
  5777   Wed 10 Jan 2018 08:34:27 Apiwat Pinyoyang Wed 10 Jan 2018 08:00:16 Beam OperationMachine Operation Note Beam Injection Completed 07:30 Test run SYN only (Isyn =  18
mA)

08:00 Dump beam @ 64 m.A.
 2018-01-10-0845.PNG 
  5776   Tue 09 Jan 2018 20:43:50 Somkiat Wisaiphion Tue 09 Jan 2018 20:00:31 Beam OperationMachine Operation Note Beam Injection   19.35 Test run SYN (Isyn 20 mA)

20.00 Dump beam @ 66.5 mA

20.02 Warm up HBT, STR, MPW and
 2018-01-09-2043.PNG 
  5775   Tue 09 Jan 2018 08:27:45 Apiwat Pinyoyang Tue 09 Jan 2018 08:00:30 Beam OperationMachine Operation Note Beam Injection Completed 07:30 Test run SYN ===> ok (Isyn
=  20 mA)

08:00 Dump beam @ 68 m.A.
 2018-01-09-2043.PNG 
  5774   Mon 08 Jan 2018 20:48:05 Somkiat Wisaiphion Mon 08 Jan 2018 20:00:50 Beam OperationMachine Operation Note Beam Injection   19.14 Test run SYN (Isyn 20 mA)

20.00 Dump beam @ 61.7 mA

20.02 Warm up HBT, STR, MPW and
 2018-01-08-2046.PNG 
  5773   Mon 08 Jan 2018 08:44:40 Apiwat Pinyoyang Mon 08 Jan 2018 08:00:23 Beam OperationMachine Operation Note Beam Injection Completed 07:30 Test run SYN only (Isyn =  20
mA)

08:00 Dump beam @ 54 m.A.
 2018-01-08-43.PNG 
  5772   Sun 07 Jan 2018 18:40:36 Somkiat Wisaiphion Sun 07 Jan 2018 17:49:26 Beam OperationMachine Operation Note Beam Injection   17.49 Dump beam

17.51 Warm up HBT, STR, MPW
and SWLS magnets.
 2018-01-07-1843.PNG 
  5771   Sun 07 Jan 2018 18:39:44 Somkiat Wisaiphion Sun 07 Jan 2018 17:41:44 ProblemMagnet Note PS-SWLS fault  SOFB uncontrollable   IMG_20180107_174203.jpg 
  5770   Sun 07 Jan 2018 08:53:55 Tewarit Praneetponkrung Sun 07 Jan 2018 08:00:38 Beam OperationMachine Operation Note Beam Injection   07:35 Test run SYN only (Isyn =  20
mA)

08:00 Dump beam @ 54.1 m.A.
 2018-01-07-0851.PNG 
  5769   Sat 06 Jan 2018 20:15:45 Somkiat Wisaiphion Sat 06 Jan 2018 19:38:25 Beam OperationMachine Operation Note Beam Injection    

19.38 Warm up HBT, STR, MPW and
SWLS magnets.
 2018-01-06-2019.PNG 
  5768   Sat 06 Jan 2018 20:12:37 Somkiat Wisaiphion Sat 06 Jan 2018 07:00:17 ProblemRF Note STR RF (DLLRF) has problem  Fixed and calibration STR-RF by Chachabchum
T.
  
  5767   Tue 19 Dec 2017 20:53:56 Tewarit Praneetponkrung Tue 19 Dec 2017 20:00:40 Beam OperationMachine Operation Note Beam Injection   19.30 Test run SYN only >>> OK
(Isyn = 10 mA)

20:00 BL8 request time 10 mins
 2017-12-19-2057.PNG 
  5766   Tue 19 Dec 2017 08:36:49 Somkiat Wisaiphion Tue 19 Dec 2017 08:00:36 Beam OperationMachine Operation Note Beam Injection   07:35 Test run SYN only (Isyn =  19 mA)

08:00 Dump beam @ 69.5 m.A.

08:02 Warm up HBT, STR, MPW
 2017-12-19-0840.PNG 
  5765   Mon 18 Dec 2017 20:29:40 Somkiat Wisaiphion Mon 18 Dec 2017 20:00:27 Beam OperationMachine Operation Note Beam Injection   19.30 Test run SYN only >>>
OK (Isyn = 15 mA)

20.00 Dump beam @ 72.9 mA.
 2017-12-18-2042.PNG 
  5764   Mon 18 Dec 2017 08:27:19 Tewarit Praneetponkrung Mon 18 Dec 2017 08:00:03 Beam OperationMachine Operation Note Beam Injection   07:30 Test run SYN only (Isyn =  15
mA)

08:01 Dump beam @ 108.6 m.A.
 2017-12-18-40.PNG 
  5763   Mon 18 Dec 2017 03:35:54 Tewarit Praneetponkrung Mon 18 Dec 2017 02:47:41 Beam OperationMachine Operation Note Beam Injection   02.44 Beam dump @ 93.29 mA.

02:47 Warm up HBT, STR, MPW&SWLS
magnets.
 2017-12-18-0344.PNG 
  5762   Mon 18 Dec 2017 03:34:27 Tewarit Praneetponkrung Mon 18 Dec 2017 02:44:03 ProblemMachine Operation Note Beam dumpCompleted6202.44 Beam dump @ 93.29 mA   